The cutover weekend runbook
Cutover plans run forwards: freeze, load, reconcile, test, go. This one is built backwards,
from the last hour at which you can still change your mind. If your plan does not name that hour, it does not
have a rollback, whatever its rollback section says.
Guide · updated 2026-10-17
Rollback is modelled as a database restore. That is the wrong model. You can restore the legacy
database. You cannot restore the payment file the bank has accepted, the invoice in your customer's payables
queue, or the parcel on the carrier's truck. The real point of no return is the first document the new system
sends outside the building. Build the weekend around that hour.
The irreversibility ledger
Build this table in the week before the window, one row per outbound emission the new system can produce, with
the planned time of each. The earliest planned time is your rollback deadline. Every emission is
switched off when the window opens and switched back on individually, by name, after its own gate. That is also
how the deadline moves: by delaying an emission.
Now invert it. If the rollback deadline falls before the final load is scheduled to finish, the plan has
no rollback. It has a hope. There are two honest responses: lengthen the window, or cut the scope that
goes live in it. Patching the estimate is not one of them. Run the test on the plan in front of you. Note first
what the test needs in order to be runnable at all: a restore duration measured on production-scale data. A plan
that cannot state that number cannot sit the test, which means its rollback is an assertion rather than a
plan.
A mock cutover is recommended everywhere. The question worth asking first is what result would force a replan,
because a rehearsal with no failing result is theatre. This is the failing result. The rehearsal produces four
timings: the delta extract, the load in dependency order, reconciliation to a signed answer, and a full restore
of legacy. If they do not fit inside the window with comms time on top, the rehearsal has done its job by
failing. The data migration checklist covers the load order
and the reconciliations behind those timings.
Asymmetric authority, signed before the window
Naming one person as the owner of the rollback call is not the same as making the call operable at 03:40, when
that person does not answer. Two rules close the gap, both signed before the window opens.
The authority is deliberately asymmetric. The cutover manager may call a rollback alone. The
cutover manager may never declare go-live alone. Go-live needs three signatures in the room: the sponsor, the
controller for balances, and operations for shipping. The risk-reducing call is allowed to sit lower in the
hierarchy than the risk-taking one. Check your own governance document for this: where it sets one quorum for
both calls, the safe call is the one that cannot be made quickly.
Silence defaults to rollback. Write the ladder with a clock on it: sponsor, then the named
alternate, and after a stated number of minutes with no contact the cutover manager rolls back by default.
Default-to-proceed is how a business discovers on Monday that it went live on a decision nobody made.
The decision packet
A gate becomes an argument when the sponsor is handed a status report instead of a decision. The fix is one
page, the same six lines at every gate, in the same order, rehearsed so the format is familiar before it
matters.
- Trial balance variance, one number, against the source report.
- Receivables and payables open-item variance, by document count and by value.
- Inventory variance, by item and location, never in total: totals hide offsetting errors.
- Interface status, one line each, naming the emission it enables.
- Smoke test result, pass or fail, by department.
- Minutes remaining to the rollback deadline.
The last line is the one a status report never carries, and the one that turns a debate into a decision. A
defect argued about with ninety minutes of rollback left is a different object from the same defect with ten.
Three exits, not two
Cutover is written as a binary, go or roll back. There is a third exit, and it is missing from the plan rather
than from reality. Because it is unnamed it gets taken badly: informally, by whoever is loudest in the room, with
no end date and nothing written down.
Each exit needs its message to customers, carriers and the bank drafted before the window opens, because nobody
writes well at four in the morning. Three short drafts, with the blanks limited to a date and a scope.
The freeze log and the replay rule
“Freeze the legacy system” is written as if the business stops. It does not. A customer calls, a truck
has to leave, somebody authorises an urgent payment. No plan says where that is recorded while both systems are
closed.
One numbered log, on paper or in one shared sheet, nothing else. Each line carries a timestamp in the canonical
timezone, the document type, the originator and the amount, and is keyed into neither system. After the decision,
one named person replays the log into whichever system turned out to be canonical, ticking back to a count.
Two rules make it real. The log is numbered, so a missing line is visible rather than merely absent. And if it
passes an agreed number of lines, that is itself a no-go signal: the window is longer than the business can hold
its breath. An unlogged freeze is how post-go-live duplicates and missing shipments get manufactured, by a
mechanism worth stating plainly: the same urgent order keyed twice by two people who each assumed the other had
not, and the shipment nobody keyed at all because it was handled on the telephone.
Disjoint document number ranges
Invoices, credit notes, journals and cheque stock in the new system start at a range that cannot overlap legacy.
The reason is specific to rollback. Overlapping ranges make a rollback a collision: two documents carrying one
number, one of which a customer already holds. Disjoint ranges make it a gap, which an auditor can see.
Two calls belong with this and sit outside anybody's obvious remit. Somebody tells the bank about the new cheque range in
advance, or the first cheque is returned. And somebody files the new e-invoicing sequence with the tax authority
before the first invoice: a retrospective filing is a correction, not a registration.
What “within tolerance” has to mean
Go or no-go tables say “reconciled within tolerance” and leave it undefined, or demand everything ties
to the penny. Both are unworkable. Split by object.
| Object | Rule at the gate |
| General ledger trial balance | Zero variance. No exceptions, no sign-off available |
| Receivables open items | Zero variance, document by document, not in total |
| Payables open items | Zero variance, document by document |
| Bank balance | Zero variance against the statement |
| Inventory valuation rounding | Tolerance permitted: a stated threshold, a named variance account, the controller's signature |
| Currency translation | Tolerance permitted on the same three conditions |
Then the diagnostic that makes the table usable at two in the morning. Variance concentrated in a few
accounts or items is a mapping error. Fix the map, reload that object, stay inside the window.
Variance equal to the sum of the documents dated after the extract is a cut-time error. Patching
it writes next month's reconciliation problem; the delta extract is re-run instead.
One timezone, and the order sites freeze
Every row carries one canonical timezone, with local times in brackets. Pick it once, state it at the top, and
never write a bare time. A handover reading 02:00 means two different hours to two people, and the one who is
wrong is asleep.
Then the sequencing rule. Sites freeze in reverse order of reopening, so the first site to reopen is the
last to freeze. Otherwise the site with the earliest Monday morning carries the longest freeze, and its freeze log overflows.
Reopen order is set by local business hours, not by site size or readiness.
§
What the window owes hypercare
Two things are settled inside the cutover window and then lived with for months, which is why they belong in
this runbook rather than in the support plan that follows it.
The first is a production configuration freeze, with exactly one named person who may approve an emergency
change in production. It starts at the first posted transaction, not at the end of the weekend. An untracked
change made at 05:00 to get one department moving is what makes every subsequent defect report
unreproducible, and a war room cannot triage a defect it cannot reproduce.
The second is the list of what was deferred, written while the detail is still in the room: every defect carried
through exit three with its owner and date, every emission still switched off and the gate that will switch it
on, every line of the freeze log that was replayed by hand. Reconstructed on the Monday it is guesswork. Written
during the window it is the opening agenda of
hypercare, where it has to be reckoned with rather than quietly carried.
What hypercare covers after that, and the conditions on which it is allowed to end, are a separate question with
their own answer. The part that matters here is only this: a hypercare period given a duration and no exit
criteria is a calendar entry, not a gate, and the cutover weekend is where that distinction is either written
down or lost. Go-live is the midpoint of an implementation, not the end, which is also the argument of the
six stages.
Before any of thisA runbook this detailed is worth writing only if the business needs the system. If that is still open, start with the readiness check, twenty scored statements that say